ADB Funded Projects:
Sl. No Name of the Project
Project Reriod
Project Area
Project Cost Total (PA) & Approval Status Main Activities Implementing Org/Company
Investment Project:
1. Dhaka Clean Fuel (RPGCL)
01 Jan. 2003 – 31 Dec. 2009
Project Area: Dhaka

14856
(12799)
Approved

  1. Installation of 26 CNG Filling Station at 6 highways
  2. Procurement of 6000 CNG Cylinders
  3. Procurement of 5000 Conversion Cits
  4. Procurement of 100 CNG Buses
  5. Setting up a CNG conversion workshop
  6. Consultancy services

RPGCL

2. Installation of Compressor Station at Muchai and Ashuganj
01 Jan. 2006 – 30 Jun 2011
Project Area: Sylhet & Bramonbaria

303408.48
(20927.35)
Approved

  1. Consultancy services
  2. Land Acquisition
  3. 2 Nos Compressor Station

GTCL

3. Bonpara-Rajshahi Gas Transmission Pipeline Project
01 July 2006 – 30 Jun 2011
Project Area: Pabna, Natore & Rajshahi

1615.200
(762.906)
Approved

  1. 53 KM gas transmission pipeline with 12 inc dia meter from Bonpara to Rajshahi

GTCL

4. Gas distribution Network at Rajshahi City and its adjoining areas (Revised)
01 July 2006 – 30 Jun 2011
Project Area: Rajshahi

11262.30
(5296.10)
Approved

  1. 280 1”-8” KM Distribution pipeline
  2. Fabrication of 1 TBS
  3. Fabrication of 2 DRS
  4. Acquisation of 7.5 acrs of Land
  5. Land development, Boundary wall, Internal road etc.

PGCL

5. System Loss Reduction of TGTDCL
01 July 2006 – 30 Jun 2011
Project Area: Dhaka

2256.75
(1399.00)
Approved

  1. Acquisition of Metering Equipment
  2. Installation of Meters

TGTDCL

6. Bheramara-Khulna Gas Transmission Pipeline Project
01 July 2006 – 30 Jun 2011
Project Area: Kustia, Jessore, Zhinadha

68529.47
(32594.04)
Approved

  1. Construction of 165 km Gas transmission pipeline with 20 inch dia from Bheramara-Khulna

GTCL